PowerHouse Arcola
![](https://cdn.prod.website-files.com/656a5fbe6f543fdf7801159e/657b5a49f0edabe483ada1e3_2023.10ArcolaRender.jpg)
![](https://cdn.prod.website-files.com/656a5fbe6f543fdf7801159e/657b5a58a7f7ed92e4d92f6f_2023.11ArcolaRender.jpg)
![](https://cdn.prod.website-files.com/656a5fbe6f543fdf7801159e/65aece094ad8ac5738053c20_LocationMap_PHAshburn_web.png)
No items found.
Details & Specifications
Acreage: 30.39 Acres
Developable SF: 796,844 SF
Buildings: 2
Stories: 3
Max Utility MW Capacity: 165 MW
Delivery: August 2026
Additional Details
Site Development Timeline
Entitlements/Design
Q1 2022 - Q3 2024
Construction/Delivery
Q4 2024 - Q3 2026
Power Delivery
Q3 2026